Break the project into separate milestones
Separate supplier search, shortlisting, quotation clarification, sample preparation, sample delivery, revisions and buyer approval. Then list material availability, production, separately agreed checks, packing and shipment handover. Give each stage a completion condition. “Sample ready” and “sample approved” describe different milestones; neither automatically means production can start.
Ask which stages may overlap and which must finish first. Include time for your own review and for a new sample if a revision remains open. Do not treat a supplier’s production estimate as the length of the whole sourcing project.
- Search and shortlist: enough information to select suppliers for the next step.
- Samples and approval: identified references and recorded buyer decisions.
- Materials and production: confirmed prerequisites and proposed milestones.
- Checks, packing and handover: agreed responsibilities and remaining questions.
Record the trigger for each lead-time estimate
For every estimate, ask: what starts the clock, who confirms the trigger, and which assumptions are included? Possible prerequisites to clarify include final specifications, an acknowledged order, an agreed payment stage, material availability or sample approval. Record the supplier’s actual reply rather than assuming every project uses the same sequence.
Distinguish the date goods are expected ready from the proposed handover or arrival date. Before production, resolve the reference version, open approvals, named contacts and the next confirmation point.
Confirm the slot for this order
Before treating a production window as confirmed, ask whether the reply covers this order or only describes general availability. Add one slot-status row beside the production start trigger:
- Product and specification revision; quantity and unit; proposed production route and site.
- Supplier-reported start and finish window; prerequisites still open.
- Status: availability estimated, order-specific slot confirmed, or unanswered; the supplier's exact qualification.
- Named confirmer, reply date and reference, and the next reconfirmation date.
Illustrative distinction: “We can usually start next month” remains an estimate. Ask whether the stated window covers the named revision and quantity, and what happens if material or sample approval slips. Keep an unanswered slot question open rather than copying the date into a confirmed schedule.
SGS describes factory-quality assessments of processes and manufacturing systems; that service description does not confirm an available order slot. Use the supplier-check guide to scope specialist workload assessment separately. Do not derive available output from a machine count.
Make buyer decisions and material dependencies visible
List dependencies beside the affected stage: buyer artwork approval, material confirmation, a revised sample, a packaging decision or information from a specialist. Give each an owner and a next-action date. Ask the factory which dependency affects the next milestone and whether its estimate changes when that dependency is late. The fictional working-day calendar shows how a parallel branch or closure changes the result.
Your latest acceptable decision date is a planning assumption until the relevant parties confirm its effect. Make that distinction visible. An unconfirmed material date should remain an open item rather than becoming a precise production-start promise.
A fictional working-day calendar: what actually moves the handover?
Illustration only: these invented dates and durations are not supplier estimates or typical Vietnam lead times. Start on Monday 2 November 2026 with a frozen brief. Assume Monday–Friday work, no closures, no rework, capacity already reserved and all commercial release requirements satisfied before production. Each dependent stage starts on the next working day after its prerequisites finish.
Scroll horizontally on a small screen to view all columns.
| Stage | Start trigger | Working days | 2026 dates |
|---|---|---|---|
| Sample preparation and receipt | Frozen brief; sample route ready | 8 | 2–11 November |
| Buyer sample review | Sample received | 2 | 12–13 November |
| Production materials ready | Frozen brief; material work authorized in parallel | 12 | 2–17 November |
| Production | Both sample approval and materials ready; release conditions met | 20 | 18 November–15 December |
| Agreed checks and packing | Production completed | 3 | 16–18 December |
| Factory handover | Checks passed; packing and handover arrangements ready | 1 | 21 December |
Read the dependency: sample approval takes 10 working days; materials take 12 in parallel. The baseline therefore takes 12 + 20 + 3 + 1 = 36 working days, rather than adding both parallel branches. Materials are the controlling branch. A two-working-day delay to sample approval uses the available gap without moving production; a third day would move handover by one working day if nothing else changes.
Test a closure: if this fictional factory stops production on 26–27 November and everything else stays unchanged, handover moves from 21 to 23 December. Those are invented closure dates, unrelated to Tet. Replace them with each party’s confirmed calendar and ask whether the restart or capacity queue changes too.
For your own plan, replace every duration, owner, start trigger and closure assumption. Material work may not be allowed to start before sample approval in your project; if so, make it sequential and recalculate. Transport, import clearance and delivery to the buyer are outside this example, so 21 December is not an arrival promise.
Ask each supplier about Tet and other closures
For Tet and other holiday planning, ask each factory, material supplier and logistics provider for its own confirmed last working day, closure dates, restart date and booking cutoffs. Record these separately, including who confirmed them and when. Reconfirm any milestone that depends on the restart.
- Ask the factory for its last working date and planned restart date for this order.
- Confirm whether office replies, sampling, production and dispatch follow the same schedule.
- Ask who can answer urgent questions during the closure, if anyone.
- Confirm relevant material-supplier dependencies and when the factory will update you.
- Ask your logistics provider separately about booking, collection and document cutoffs.
Work backward from the needed delivery date
Start with the date you need the goods and the location it refers to. Ask your logistics provider to identify the transport assumptions needed to work backward to a proposed factory handover. Then work back through packing, agreed checks, production, materials and approval using supplier-confirmed estimates.
If the schedule includes a finished-lot inspection, use the pre-shipment inspection brief to confirm site access, lot readiness and the report needed before the buyer decides on handover.
Check where a confirmed closure intersects those stages. If a milestone is unknown, keep a range or open question supplied by the responsible party. Discuss choices such as moving the buying decision, adjusting the delivery target or evaluating a proposed partial handover. Obtain separate confirmation of feasibility, charges and buyer approval before changing the plan.
Keep assumptions, owners and updates in one schedule
Keep the original estimate beside the latest update so changes remain visible. Record holiday assumptions with their source and confirmation date. Add the decision needed if an assumption fails, who will make it, and when the next check is due. Refresh affected stages together; changing only the final date hides the dependency that moved.
Production timeline record
Keep each milestone estimate beside its assumptions.
- Milestone
- Add milestoneMilestone and completion condition
Timing basis
- Start / dependency
- Add start / dependencyStart trigger and dependency
- Estimate / source
- Add estimate / sourceEstimate, source and date received
- Buyer target
- Add buyer targetBuyer target and confirmed status
Confirmation and next decision
- Cutoff confirmation
- Add cutoff confirmationClosure/cutoff confirmation and responsible contact
- Open question
- Add open questionOpen question, decision owner and next update
- Decision to revisit
- Add decision to revisitIf the assumption changes, decision to revisit
Copy this template to complete in your own document.